Use this mockup and sample review reviewer checklist to document fit, finish, limitations, decisions, and outstanding actions.

Posted At: Mar 21, 2025

Mockup and Sample Review: Reviewer Checklist

Mockup and Sample Review: Reviewer Checklist

Physical review answers a narrower question than product acceptance. A mock-up or sample can expose geometry, interfaces, finish and handling; it cannot establish installed performance or authority approval. This mockup and sample review reviewer checklist turns that distinction into an auditable record for the door-hardware consultant. Use it during the physical lock mockup review to state what the sample demonstrated, what it did not, and who must close each remaining issue.

Direct answer. Short version — mockup and sample review reviewer checklist is treated here as mockup and sample review reviewer checklist first. mockup-and-sample-review comes second. The evidence for mockup and sample review reviewer checklist is named in the sections below. A mockup and sample review reviewer checklist gives the specifier working documents. mockup and sample review reviewer checklist is the document that decides the requirement. That is what mockup and sample review reviewer checklist turns into.

CONFIRM-WITH-LOCAL-BUILDING-CONTROL: Confirm which authority, if any, reviews the installed door set; this checklist records physical sample evidence only.

Memo scope and decision boundary

This memo supports a review that connects the client, installer and supplier without replacing site verification. Its decision is whether the sample is acceptable as evidence for the stated review scope. What the specification covers is in the smart door locks.

Memo fieldWorking position
PurposeReconcile physical evidence with the specified door set and submittal
Review ownerDoor-hardware consultant or other named reviewer
Decision audienceClient’s design and procurement representatives
Evidence cutoffFit, finish, interfaces and handling within the agreed review conditions
Explicit exclusionInstalled performance, site conditions and authority acceptance

Identify the door leaf, frame, hardware and locks by their schedule references. A sample without a traceable door-set reference cannot be compared reliably.

Evidence the sample can and cannot settle

A mock-up is evidence of fit and finish when its conditions are documented. It is not a performance certificate. Keep the evidence boundary visible so a reviewer does not convert a favorable visual inspection into an unsupported acceptance.

Evidence areaWhat the sample may establishWhat remains unresolved
Dimensional fitWhether the sample interfaces match the stated dimensionsWhether the actual door and frame match those dimensions
Faceplate and strikeWhether the supplied closing-edge components form a matched pairAlignment after installation on site
FinishWhether the physical sample visually matches the agreed referenceThe approved production finish unless separately confirmed
OperationHow the included components operated during the agreed checkPerformance under site power, network and usage conditions
AccessoriesWhich parts were present for the reviewWhether every required interface is supplied
DocumentationWhether the sample can be reconciled to a dated submittalWhether the delivered product will match that revision

Smart lock sample approval therefore means that the sample passed the agreed fit-and-finish checks within the recorded conditions. It does not approve the installation, the complete submittal or an unseen product revision.

Intake gate before the sample arrives

Treat missing information as a review finding rather than filling gaps during the meeting.

  1. Identify the door set. Record the opening reference, door schedule, frame type and intended lock arrangement.
  2. Reconcile the sample. Capture the manufacturer, model or SKU, sample identifier, finish and hardware revision against the current submittal and dated product page.
  3. Obtain dimensional evidence. Require the backset, bore diameter, bolt-to-bore distance, faceplate and strike references, units and stated tolerances.
  4. Identify the finish. Provide the RAL or colour reference, approved sample and any assembly instructions governing concealed or adjacent surfaces.
  5. Set the review criteria. List which items must be inspected physically and which remain document or authority reviews.
  6. Assemble the door hardware submittal record. Include the review request, product evidence, drawings, door-set references and outstanding questions.
  7. Schedule the record owner. Name the reviewer, attendees, evidence custodian and person authorized to close actions.

The supporting evidence request can be cross-referenced with Mockup and Sample Review: Documents a Specifier Should Demand.

Review workflow and stop points

The workflow should expose incomplete evidence before it reaches a physical approval decision.

flowchart TD
    A[Set review scope] --> B{Evidence package complete}
    B -->|No| C[Return incomplete package]
    B -->|Yes| D{Sample identity matched}
    D -->|No| E[Hold sample comparison]
    D -->|Yes| F[Check fit and finish]
    F --> G{Exceptions recorded}
    G -->|No| H[Record approval decision]
    G -->|Yes| I[Assign corrective actions]
    I --> J{Actions closed}
    J -->|No| K[Keep decision conditional]
    J -->|Yes| H

A return-for-completion decision preserves the original review scope. A conditional decision identifies the exact condition, owner and evidence required for closure. Neither decision should conceal an unresolved identity or dimensional discrepancy.

Using the reviewer checklist line by line

This mockup and sample review reviewer checklist supports fit and finish verification without implying a test of the installed assembly. Record the evidence reference beside each result so a later reader can reconstruct the decision.

Review checkEvidence enteredPass condition
Scope and door setOpening, schedule and drawing referencesAll references identify the same door set
Sample identityManufacturer, model or SKU, sample ID and revisionDetails reconcile to the submitted package
BacksetDistance from door edge to spindle or cylinder centreDatum and unit match the door documentation
Bore diameterSeparate dimensional calloutValue, unit and tolerance are stated independently
Bolt-to-bore distanceSeparate dimensional calloutValue is not inferred from the bore diameter
Faceplate and strikePaired component referencesSupplied pair matches the intended assembly
Case configurationMortise, rim or multipoint identificationConfiguration agrees with the submittal
Door contextThickness, material and relevant clearancesMock-up conditions represent the stated design
Finish referenceRAL or colour reference and physical sampleSample is compared with the stated reference
Physical fitObservations at each door or frame interfaceNo unexplained interference or mismatch remains
Operating checkAgreed sequence and observed return positionsResult is limited to the agreed manual check
AccessoriesIncluded reader, spindle, strike or other componentsPhysical contents match the review inventory
Evidence packageDated product page and supporting documentsEach product fact has a traceable source

A blank field means the item was not reviewed. Do not convert a blank into an assumed pass. If the sample differs from the submittal, record the difference and reopen the relevant submittal item.

Decision comparison and sample review

The reviewer should choose a decision that matches the evidence rather than the desired schedule outcome.

DecisionMinimum evidenceRecorded consequenceNext control
Accept for stated scopeAll scoped checks completed with no open exceptionSample evidence is accepted for that scopeRetain the package and closure record
Accept with conditionsFit and identity are established, with bounded exceptionsApproval applies only to the recorded conditionsAssign owner, due date and closure evidence
Return for revisionMissing or conflicting evidence prevents comparisonNo sample decision is issuedCorrect the package and repeat the review
Reject the sampleIdentity or design conflict cannot be reconciled within scopeSample is excluded from the evidence setRecord the conflict and initiate a new review

The decision must distinguish sample acceptance from product or installation approval. The submittal is not approved until the review is recorded and dated.

Discrepancy and exception log

Attach the exception log to the review record. Use one entry for each observable difference so that closure can be traced without rereading meeting notes.

Log fieldRequired entry
Finding IDUnique reference
LocationOpening and door-set reference
ObservationPlain description of the condition
RequirementDrawing, dimension or finish reference
Proposed correctionSpecific action offered for review
OwnerNamed person responsible
Due dateAgreed closure date
StatusOpen, verification pending or closed
Closure evidenceDocument, photograph or revised record
Reviewer confirmationName and dated confirmation

Keep observations separate from conclusions. For example, record the observed gap before proposing a revised dimension or alternative component.

Routing unresolved questions

Some findings need evidence from outside the review meeting.

  • Site conditions: Use an Office Smart Lock Site Survey or Smart Lock Retrofit Site Survey to obtain the door and frame facts needed for comparison.
  • Product evidence: Give the supplier a precise question and request a dated, revision-specific source rather than a verbal capability statement.
  • Authority decisions: Keep installed-door acceptance outside the sample record and route it to the responsible reviewer.
  • Finish decisions: Ask the client or design lead to confirm the governing colour reference and the surfaces included in that reference.

CONFIRM-PER-SUPPLIER: Confirm any connected-function or accessory capability against the dated product page for the specific SKU.

CONFIRM-WITH-LOCAL-FIRE-AUTHORITY: Confirm any fire-door or egress-related acceptance separately; the sample review does not decide it.

CONFIRM-WITH-LOCAL-ACCESS-CONSULTANT: Confirm the operable-part and access criteria for the installed assembly.

Build the mock-up approval log

The reviewer should create the log as the meeting proceeds rather than reconstruct it afterward. The wider sequence is set out in Mockup and Sample Review: A Smart Lock Specifier Guide.

Include these fields:

  • Review identifier, revision, date, location and attendee roles
  • Door-set, sample and submittal references
  • Evidence index and photograph references
  • Check results and discrepancy identifiers
  • Decision, conditions and action owners
  • Final file location and responsible record holder

A photograph shows the finish; it does not specify it. Preserve the approved reference alongside the image, and preserve the dated review record alongside both. If the sample is returned, transferred or replaced, record that custody change so a later reader knows which physical evidence supported the decision.

Readers comparing approaches usually start with smart lock manufacturer for apartment projects. That is the same question mockup and sample review reviewer checklist has to answer here.

Closeout and final sign-off

Close the review only after each accepted condition has closure evidence and the reviewer has confirmed it.

RoleRecord before closeout
ReviewerCompleted checks, decision and exception history
InstallerDimensional or fit input required for site feasibility
Client or design leadFinish and selection acceptance within its authority
SupplierRevised evidence and corrections attributable to the supplied sample

Issue the completed reviewer checklist with the submittal record, not as an informal attachment. A clear boundary lets the client reuse the decision, lets the installer identify field checks and gives the supplier an exact route for closing the next revision.

Put the answer on paper and request a quote against that document.