Most sourcing delays begin before the first email reaches a factory. A buyer has a door schedule, a rough door count and a brand idea, and no way to turn those into a specification a factory can quote. The five tools on this page exist to close that gap in the buyer's own office: a checklist, a door survey sheet, a quantity calculator, a comparison sheet and an RFQ pack. Used in order, they produce a request that a factory can answer in one reply instead of six.
The tools are plain documents. They contain no pricing, no promise of availability and no substitution for a site survey. What they do contain is the arithmetic and the field list that make a quotation comparable, so that two suppliers are quoting the same product rather than two interpretations of it. Everything here is free to use, and none of it requires a sales call.
The sequence is deliberate. Each tool produces the input the next one needs, and skipping a step usually means returning to it later with worse information. The table names the tool, the question it answers, what the buyer has to fill in, and the point in the process where it is used.
| Step | Tool | Question it answers | What you fill in | When to use it |
|---|---|---|---|---|
| 1 | Specification checklist | What does the factory need to know before it can quote a model | The 24 fields in section 3, completed for one building or one door type | Before any supplier conversation, and again for each new building |
| 2 | Door survey sheet | Does the door physically accept the lock | Leaf thickness in mm, backset in mm, frame profile, existing holes and handing, one row per door | After the checklist, before the model list is fixed |
| 3 | Quantity calculator | How many locks, spares, encoders, cards and gateways the project needs | Door count, issuing desks, spare ratio, card rules and building density | Once the door count is reliable, before the RFQ is sent |
| 4 | Comparison sheet | Which of two models is better for this project, on paper | Two model codes and a score against seven weighted criteria | After two quotations are on the table |
| 5 | RFQ pack | What exactly am I asking suppliers to quote | Checklist, survey summary, quantities, comparison weights and the destination market | At the point of sending the request |
The order matters most between steps 2 and 3. A quantity calculator run before the door survey produces a number that looks precise and describes a door that may not exist. The two are done together, on the same visit, and the checklist is what tells the surveyor what to measure.
Buying guides, start here
How to verify a supplier before you pay
Importing from China: the practical sequence
Measuring a door before you orderEach tool is one page or one spreadsheet, and each has a single output. The descriptions below state what the output is, because that output is what the next step consumes.
The checklist is the only tool that is mandatory. The other four assume it has been completed, and a comparison sheet filled in without a checklist is a preference ranking rather than a sourcing decision.
The list is grouped by the decision each field serves. It is written for a hotel, apartment or residential project with a card, fingerprint or keypad lock; a project with a 4G lock or a glass-door lock adds a field or two and removes none. The right-hand column explains why the factory cannot proceed without the answer, which is the part buyers tend to skip when they send a one-line enquiry.
| Group | Field | Why the factory needs it |
|---|---|---|
| Door and opening (8 fields) | ||
| Door | Leaf thickness in mm | Decides whether the escutcheon and mortise fit; the working range for most interior leaves is 38-55 mm, and a leaf outside it changes the product |
| Door | Door width and height in mm | Sets the centre height of the lock and whether a vertical handle is usable |
| Door | Backset in mm, usually 60 mm or 70 mm | Decides the mortise type and whether the existing prep can be reused |
| Door | Mortise or latch type | A No. 2 hotel mortise and a tubular latch are different products with different cut-outs |
| Door | Handing (left or right, inward or outward) | The latch and the inside lever are handed; a wrong handing is a site failure, not a warranty claim |
| Door | Frame material and profile | Steel, aluminium and timber frames take different fixings, and a hollow frame cannot carry a self-tapping screw |
| Door | Fire rating of the leaf | A fire-rated leaf moves the requirement to a tested assembly under UL 10C, NFPA 80 or EN 1634-1, not to a standalone lock |
| Door | Existing holes or preparation | A retrofit and a new door are different installation scopes, and the hole pattern decides which model can be fitted without cutting |
| Credential and software (6 fields) | ||
| Credential | Credential types needed | Card, fingerprint, keypad, app and mechanical key are different hardware, and the mix decides the model family |
| Credential | Card technology | MIFARE Classic and DESFire EV2 are different security levels on the same 13.56 MHz interface, and the choice fixes the encoder and the card supply |
| Software | Software ownership model | Standalone, PC-linked encoder, TTLOCK or Tuya changes what the property has to run and who holds the database |
| Software | Integration target | A PMS link, Wiegand 26/34, OSDP or MQTT decides whether the lock is a closed system or part of a building platform |
| Software | Door and user count | Sizes the database, the number of cards and the number of administrator accounts |
| Software | Language of the app and the admin screen | A property that cannot read the menu will call support instead of using the system |
| Environment and compliance (5 fields) | ||
| Environment | Ingress protection requirement | An exterior gate or a pool-side door needs an IP-rated enclosure under IEC 60529; an interior door does not pay for it |
| Environment | Indoor or outdoor position | Sun, rain and salt air change the finish and the seal, and the model list follows the exposure |
| Compliance | Destination market and standards | The market decides which reports and declarations are requested, from FCC Part 15 to CE marking and UKCA |
| Compliance | Fire-door standard where applicable | A project with fire-rated corridors needs the assembly evidence, and the door supplier's listing governs |
| Environment | Power preference | 4 AA alkaline batteries, rechargeable packs and lithium cells suit different service models; the choice affects the battery service interval |
| Commercial (5 fields) | ||
| Commercial | Quantity by model | A single total hides the model mix, and the mix decides material planning and the MOQ conversation |
| Commercial | Spare ratio | The planning default of 1 spare lock per 50 doors is a line item, not a rounding error |
| Commercial | Branding and packaging | A logo change is a private-label layer; a housing change is a new model with its own document question |
| Commercial | Destination, Incoterm and shipping mode | Sea and air change the packing, the carton strength and the delivery plan |
| Commercial | Installation window and phasing | A project installed floor by floor needs batch shipments and batch programming, not one delivery |
Two fields are commonly answered with a drawing instead of a number: leaf thickness and backset. A drawing is acceptable only when it carries a dimension and a scale. A 2 mm error in backset is a mortise that does not align with the door prep, and the correction happens on site at the installer's rate.
The calculator uses six rules and one worked example. The rules are planning arithmetic, not a quotation; the confirmed bill of quantities follows a surveyed door schedule. The example uses 200 doors, two issuing desks and a hotel-style card system, because those numbers make the spare and card allowances visible.
| Output | Rule | Worked example at 200 doors | Margin note |
|---|---|---|---|
| Locks | 1 lock per door | 200 locks | Add door-type exceptions before ordering; a bathroom door may not need a reader at all |
| Spare locks | 1 spare per 50 doors | 4 spare locks | Quoted as a separate line; held on site rather than ordered one failure at a time |
| Encoders | 1 encoder per issuing desk | 2 encoders at 2 desks | A second desk is a redundancy decision as much as a capacity decision |
| Guest cards | 2 cards per door at handover | 400 cards | Cards are consumables; the handover quantity is a starting stock, not a lifetime supply |
| Staff cards | 1 staff card per 10 doors | 20 staff cards | Add 5% for loss and replacement: 420 cards become 441 |
| Gateways | 1 gateway per 30 doors indoors, 1 per 15 where walls are dense | 7 gateways, or 14 in a dense building | A site survey decides the real number; the calculator only brackets the order of magnitude |
| Batteries | 4 AA cells per lock | 800 cells for the first fit | Cells are cheap and a low-battery alert does not fix itself; stock a service batch |
Two rules need a sentence of explanation. The spare ratio is a service decision: a property that can wait weeks for a replacement part needs a larger pool than one with a local distributor, and the calculator does not know which property it is. The gateway rule is a radio estimate: 1 per 30 doors assumes a normal corridor with plasterboard partitions, and 1 per 15 assumes concrete or steel that attenuates the signal. Neither number replaces a site survey, and a building that mixes both should be counted by zone.
The card allowance has a hidden cost that the calculator makes visible. Cards are issued, lost, kept by departing staff and reprinted, so the handover stock is the smallest number in the card line. Buyers who want to compare suppliers should ask for the card unit price and the card encoding time in the same request, because a cheap lock with expensive cards is a different total cost.
Comparison sheets
Glossary of lock terms
Standards reference
Market entry notesA comparison sheet is useful only when the weights are fixed before the scores are known. The weights below are a starting set for a project buyer; a distributor would raise the landed-cost weight and lower the installation-support weight, and that change should be written down before the quotations arrive. Each score needs an evidence line, because a score without evidence is a preference.
| Criterion | Weight | How to score 1-5 | Evidence to record |
|---|---|---|---|
| Door fit | 20% | 5 where the model fits the surveyed doors without modification; 1 where the door has to be re-cut | Survey rows covered, backset match, handing |
| Credential and software | 20% | 5 where the credential mix and the software model match the property's routine; 1 where a workaround is needed | Credential list, card technology, admin screen language |
| Compliance documents | 15% | 5 where the model pack answers the tender clauses; 1 where key reports are missing | Document list per model, standard editions |
| Serviceability and spares | 15% | 5 where consumables and spare parts are catalogued by model and batch; 1 where parts are unlisted | Spare list, battery type, part lead time basis |
| Landed cost | 15% | 5 for the lowest total cost at the same scope; 1 for the highest | Unit price, packing, freight basis, card cost |
| Lead time and capacity | 10% | 5 where the quoted window covers the installation start; 1 where it does not | Quoted lead-time basis, phasing plan |
| References and support | 5% | 5 where comparable projects and a training route exist; 1 where neither is offered | Case references, training modules, support tiers |
The arithmetic is the easy part. A model scoring 4, 3, 4, 3, 2, 3 and 4 against those weights produces 325 points out of 500, or 65%. A second model scoring 3, 5, 3, 4, 4, 2 and 3 produces 360 points, or 72%. The second model wins on paper, and the first model wins on landed cost and lead time. That is the point of the sheet: it shows which two criteria are carrying the decision, so the buyer can check whether those two are really the ones that matter.
Three rules keep the sheet honest. Score the same model variant in both columns, because a base model against a premium model is not a comparison. Record the evidence for every score above 3 or below 2. Re-run the weights after the site survey, because a constraint discovered on site can change what a project values. The model families the sheet is usually run against are listed at products, and the scenarios are mapped at applications.
The tools are designed to be used before a supplier conversation, and most of them work without one. The checklist, the quantity rules and the scoring weights are on this page and can be copied into a spreadsheet in 15 minutes. Model parameters are published with the model pages, and the document list for a model is obtainable through the document route described at compliance documents.
Three conditions apply. First, no tool produces a price: pricing is a quotation, and a quotation follows a completed checklist and a quantity table. Second, no tool confirms availability: the MOQ policy is confirmed in writing with each quotation, and lead time is quoted per order and depends on model mix, finish and customization. Third, no tool replaces a sample: a sample against the surveyed door is the only way to confirm fit and software behaviour, and the route for that is order samples.
Where a buyer wants the model list before filling the checklist, the catalogue request is at request the catalog. Where the project is already defined and the buyer wants a quotation, the request form is at request a quote. Neither route asks for a meeting, and neither route gates the tools behind a registration.
Not included: the tools below are planning aids. They do not perform the work that a site, a laboratory or a contract has to perform.
The limit that matters most is the first one. A checklist completed from an architect's drawing looks complete and can still be wrong on every door, because drawings describe a nominal leaf and sites contain actual leaves. The correction is cheap before the order and expensive after it.
Four checks confirm that the tool set produced something usable rather than something tidy. They can be run before the RFQ is sent, and each one produces a specific correction if it fails.
| Check | What to inspect | What a usable output shows |
|---|---|---|
| Field completeness | The 24-field checklist | No field blank and no field answered with a range where a number is available; unknowns are marked as unknown rather than guessed |
| Survey match | Survey sheet against the checklist | Every door row carries a thickness and a backset, and exceptions are listed separately from the standard doors |
| Arithmetic | The quantity table | Each line shows its formula, the totals reconcile, and spares, cards and gateways appear as separate lines |
| Evidence behind scores | The comparison sheet | Every score above 3 or below 2 has a document, a sample or a quotation line behind it |
Evidence check: a tool set is ready to send when a supplier can answer it without asking a question about the door, the credential, the quantity or the market. That is the standard the RFQ pack is built to, and it is the standard the reply will be measured against. If a supplier replies with questions the checklist already answers, the checklist was not attached.
No. The checklist, the quantity rules and the scoring weights are published on this page and can be copied into any spreadsheet. A catalogue request is a separate action for buyers who want the model list with parameters.
Start with the checklist and fill the door and credential groups first. Those two groups decide the model family, and a model family is what a quotation needs. The quantity calculator follows once the door count is confirmed.
No. It produces quantities: locks, spares, encoders, cards, gateways and batteries. Price depends on the model, the finish, the quantity and the destination, and it is confirmed in writing with each quotation. A buyer who needs a budget figure should send the quantity table with the RFQ and ask for a budget quotation against it.
It is a bracket, not a measurement. The rule assumes a corridor with plasterboard partitions; dense concrete or steel can halve the coverage, and a mixed building should be counted by zone. The number of gateways is confirmed at the site survey, and the calculator only tells the buyer whether to plan for 7 or 14 at 200 doors.
Yes, by running the sheet twice: model A against model B, then the winner against model C. Scoring three columns at once tends to flatten the differences and hide the two criteria that decide the project. Keep the weights fixed across both runs, otherwise the comparison is between three different questions.
Partly. The checklist adds an ingress protection field and a door-material field, and the model pages carry the specific products for frameless glass and aluminium patio doors. A glass door and a gate still need a site measurement, because the fixing points and the frame profile decide the model more than the catalogue does.
From the model file. The certificate belongs to the model, not to the factory, so the list is produced per model code and states what exists and what does not. The route to request it is compliance documents, and the market logic behind it is at certifications.
Yes. The checklist and the scoring sheet are intended to be shared, and a buyer who sends them to a client or a contractor is using them as designed. What should not be shared is a model-specific quotation or a document pack marked for review, because those carry commercial terms and a scope that belongs to one project.
Fill the 24 fields, run the survey against them, calculate the quantities and send the result with the RFQ. The reply will be a quotation that answers the specification rather than a general model list, and the comparison sheet will then have two real quotations to score. That sequence is the whole method, and it works with any supplier, not only with this one.
If a field cannot be answered yet, mark it unknown rather than leaving it blank. An unknown field is a question the quotation should address; a blank field is a question nobody will notice until the doors arrive.
Send the completed checklist with the door count and the destination. The reply is a quotation against the specification and a document list for the model.
Current MOQ policy is confirmed in writing with each quotation, and lead time is quoted per order and depends on model mix, finish and customization.